I answer questions related mainly to civil engineering, including transport, environment, etc, correlating the Conditions of Contract with applicable Law of the Country, where a project is being developed, including procurement issues. Correlation is also made with eventual other internationally concerned issues, such us procedures of an International Financing Body, such as Development Banks, EU, etc. All I need is a clear question and sufficient details concerning your problem and applicable Conditions of Contract and Law.

r sivaraman

Saudi Arabia
I can answer questions related to construction contract formation, contract management, dispute resolution especially arbitration, contract closure procedures i can not answer question on price negotiation prior to forming contracts

Recent Answers

2016-09-26 Fidic1999-Sub-clause 1.5 :Priority of Documents:

Mr Hussein,  Certainly NOT because it is part of contract and Engineer does not have the authority to amend the contract. The contract is normally between the Owner and the Contractor.However, if there

2016-09-22 PC rate:

Mr Hussein,  Sorry for the late response.  I am giving straight answer to your question. When the contractor submitted the sample, as Engineer, you had given approval for quality, colour, texture, etc