Muhammad Taimoor AlamPakistan
Available
|
Questions related to technical tools of primavera P3, resource loading, cost loading, preparing and monitoring the baselines, contractual correspondence linked to primavera, how to use custom ideas in the programs. Most important is the link between the activities as per given specs and preparation of claim as per Contract FIDIC linked with plan on primavera Plus question related to contracts, regarding claims specially associated with time extension, taxation,deductions on Payment certificates can be entertained.Also questions related to Primaver 6 are entertained. |
Dear Asad, The comments of your client cannot be implement strictly. There are many activities specially those having (Start to start lag)which may not start strictly as per the lag. "Activity started
Dear Asad, Thanks for your question.no need to worry this generally happens while updating.But if you think that the logics have changed too much practically then U can modify the links as per revised
Dear, Please let know which % u have allocated to WBS ? for proer way as i explained above to go through the activity resource dictionary and so on. this will help a great deal.for s curve u can
Thanks for your question. It may be due to multiple reasons.when i used to assign (baseline and comparing update) i would make sure: 1 - Assign MUST FINISH DATE to the project. 2- Check the
Abnormal rains will only be considered for EOT claim.Regular rains will not entitle the contractor for EOT as it is covered in the the tender price. Every contractor needs to investigate the prescribed