Construction Law/Expert Profile


Ask A Question

John Dowse

U.K.
Available

Follow me on:
  

Expertise

Legal; contract interpretation; quantum; delay analysis. Practitioner in arbitration, adjudication and mediation.

Experience in the area

Thirty-three (33) years experience in building and construction, at all levels both within contracting and consulting organisations. Practising arbitrator, adjudicator, and mediator. Faculty approved trainer for the Chartered Institute of Arbitrators. Lecturer on construction contract forms and dispute resolution practices.

Organizations

Chartered Institution of Civil Engineering Surveyors Chartered Institute of Arbitrators Institute of Directors Society of Construction Arbitrators

Publications

Various UK and International construction and legal publications.

Education/Credentials

LLB (Hons), Pg Dip (Legal Practice), MCInstCES MCIArb MIOD Barrister

Average Ratings

Recent Reviews from Users

Read More Comments

    K = Knowledgeability    C = Clarity of Response    P = Politeness
UserDateKCPComments
Sudantha12/08/16101010 
Sudantha12/02/16101010 
Dilum12/01/16101010Thank you very much sir.
Shantha11/16/16101010Thank you very much sir. You have .....
Sudantha11/09/16101010 

Recent Answers from John Dowse

2016-11-27 Interim Payment Certificate:

Dear Dilum,    Thank you for this question.    As I am sure you are aware, the FIDIC contract form requires that the Contractor submits supporting details with his Statement. If the format of the Statement

2016-11-18 S & HO Overheads:

Dear Sudantha,    Thank you for this question.    To answer this you need to understand that an extension of time claim accrues only when the event causes a delay to the date for completion. If there is

2016-11-08 Inconsistents between CESMM3 & Preamble to BOQ:

Dear Shantha,    Thank you for this question.     I have been struggling to find a simple answer. It seems as though whoever has drafted the preambles is attempting to hide inadequacies in the Bill of

2016-11-06 FIDIC 1999/1987:

Dear Sudantha,      Thank you for this question.    You will not find any reference within the FIDIC contracts to a mobilisation period as being separate or apart from the contract period/Time for Completion

2016-10-29 FIDIC 1999 MOS:

Dear Sudantha,    Thank you for this question.    I assume that you intended to refer to sub-0clause 14.5 rather than 13.5. Whilst the determination is for the Engineer to make it is commonly made by reference

 

Ask A Question

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


©2016 About.com. All rights reserved.