Construction Law/Expert Profile


Ask A Question

Expertise

Anything related to extensions of time and delay analysis.

Experience in the area

45 years in the Construction Industry 15 Years as a consultant delay analyst - I now hold myself to be expert in this field.

Organizations

Society of Construction Law Adjudication Society ex Planning Engineers Organisation

Publications

6 articles on the relevance of the India Contract Act 1872 and its relevance to modern construction in India. Waiting Publication

Education/Credentials

Associate Member of the Institue of Building

Past/Present Clients

Currently employed in India by Punj Lloyd as expert delay analyst. Engaged in ongoing arbitrations and EoT claims. Prior an Indepenent consultant in delay analysis.

Average Ratings

Recent Reviews from Users

Read More Comments

    K = Knowledgeability    C = Clarity of Response    P = Politeness
UserDateKCPComments
Sudantha12/28/16101010 
Sudantha12/03/16101010 
Sudantha11/18/16101010 
Sudantha11/11/16101010 
Sudantha10/29/16101010 

Recent Answers from Mike Testro

2017-01-05 Contemporary Delay Responsibility:

Hi Tamer  Your simple question has an encyclopaedia of potential answers attached to it.  I will try to give you a simple and short answer.  1. Read your contract which will tell you which of the contracting

2016-12-28 Claim on idle tools:

Hi Harrison  From your description it appears that these are two stand alone contracts - each independent of the other.  You therefore have a clear suspension order on Contract A for a considerable period

2016-12-27 Prolongation Cost:

Hi Sudantha  Basic rules of concurrency.  1. Any relevant delay caused by the Employer will always entitle the Contractor to an EoT.  2. The Contractor will only get costs for the period where the Employer's

2016-11-18 Contractual Claim:

Hi Sudantha  The principles are very simple.  1. If the duration of the delay event is 10 weeks  2. If the delay effect after completion date is 8 weeks  Then 8 weeks of site costs are placed within the

2016-10-29 Materials on Site:

Hi Sudantha  Interim payments for materials and plant on site is a rolling calculation which eventually resolves itself to zero so any discrepancy in the valuation is self correcting.  A contractor would

 

Ask A Question

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


©2017 About.com. All rights reserved.