Construction Law/Expert Profile


Ask A Question

Expertise

Anything related to extensions of time and delay analysis.

Experience in the area

45 years in the Construction Industry 15 Years as a consultant delay analyst - I now hold myself to be expert in this field.

Organizations

Society of Construction Law Adjudication Society ex Planning Engineers Organisation

Publications

6 articles on the relevance of the India Contract Act 1872 and its relevance to modern construction in India. Waiting Publication

Education/Credentials

Associate Member of the Institue of Building

Past/Present Clients

Currently employed in India by Punj Lloyd as expert delay analyst. Engaged in ongoing arbitrations and EoT claims. Prior an Indepenent consultant in delay analysis.

Average Ratings

Recent Reviews from Users

Read More Comments

    K = Knowledgeability    C = Clarity of Response    P = Politeness
UserDateKCPComments
John W05/13/12101010Dear Sir, Thank you very much for .....
Mohammed Mujtaba 03/28/12101010Thanks for your precious suggesion and reply
chris03/26/12101010 
Ian03/21/12101010 
Edward 03/18/12101010Thank you very much

Recent Answers from Mike Testro

2012-05-12 Time at large:

Hi John  I doubt if there are grounds to set time at large with the scenario that you have described.  When the works are suspended by the Engineer under 40.1 and permission to resume the works is then

2012-04-12 The best percentage for the penalty for delay of completion:

Hi Rafat  You say the word "penalty" but you have to be careful how you use this word because in some countries - UK and Commonwealth - penalties are not allowed. You have to use Liquidated and Ascertained

2012-04-03 Back-to-back:

Hi Marc  The term "Back to Back" although a common term in the construction industry is not clearly defined so can be open to any number of interpretations.  The actual terms and conditions regarding the

2012-03-25 Discrepancies in Sub-Contract Agreement j:

Hi Mike  You have set a number of different questions which are of a hypothetical nature.  Almost as if they are some sort of exam questions.  If your queries relate to real situations then some background

2012-03-16 Calendar vs Working Days:

Hi Ian  It is important that in any delay analysis that you differentiate between Working Days and Calendar Days.  If you check your contract definitions you will often find that the word "Days" is defined

 

Ask A Question

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


©2012 About.com, a part of The New York Times Company. All rights reserved.