I can answer queries related to Construction Contracts, Claims, Dispute Resolution Mechanisms.
I have nearly 19 years experience in Construction Contracts, ranging from mega infrastructure projects to residential buildings and commercial complexes. I have worked with major construction companies in India and now I have my own consultancy firm.
BE Civil, MMS (Finance), CFA, BGL
| User | Date | K | C | P | Comments |
|---|---|---|---|---|---|
| Dharmarajah xavier | 05/23/12 | 9 | 10 | 10 | thank you so much for the elaborate ..... |
| Cenk | 05/09/12 | 10 | 10 | 10 | |
| Cenk | 05/04/12 | 10 | 10 | 10 | |
| Saravanan | 04/23/12 | 10 | 8 | 10 | Dear sir, Thank you very much for ..... |
| Anil Puri | 04/18/12 | 10 | 10 | 10 | Thank you for the prompt reply and ..... |
Dear Cenk, What is the exact clause of recovery of advance paid? If it states a time limit by which the advance has to be recovered, such as by 85% of the Contract Progress and in pro-rata installments
Dear Cenk, We need to see the Technical Specifications for the treatment of wastages in this contract. It is always a point of debate whether wastage is included or not included in such items. The
Dear Saravanan, Unforeseeable physical conditions have a wide ambit under FIDIC and cover subsurface, hydrological, physical and man-made obstructions but do not include any climatic conditions and
Dear Niranjan, Your query can be answered only after looking at the clauses granting extension of time and clauses regarding the deduction and reimbursement of liquidated damages. Generally speaking
Dear Niranjan, Mobilisation advance misuse can be checked by properly putting the terms of monitoring the usage in the contract document. For instance, advance can be given in stages after the contractor