Construction Law/Expert Profile

Ask A Question

Wael Ghadban

United Arab Emirates

Will respond to queries related to Engineering Contracts subject to FIDIC or other Conditions, tendering and contracting, project management, residential and commercial construction, and general Civil Engineering questions. Can answer most questions related to aviation and airports as related to the Airports, Facility management.

Experience in the area

Project construction and Management Civil Aviation - Airports Airport Pavement Design and Use Residential and commercial construction ICAO and FAA regulation






MS Civil Engineering

Awards and Honors


Past/Present Clients


Average Ratings

Recent Reviews from Users

Read More Comments

    K = Knowledgeability    C = Clarity of Response    P = Politeness
Shantha10/07/16101010Thank yuo very much for the clarifications .....
Enrico Odorisio08/23/16101010 
Aruna Kathriarachchi06/03/16101010 

Recent Answers from Wael Ghadban

2016-09-07 Omission of Part of Work from the Contract:

Hi Shantha  Omitted work should not be given to other Contractor. If so, this is a major breach of the Contract and the Contractor would be liable to an extended list of loses and disturbances.  However

2016-08-22 FIDIC_Cascade Sub-Contracting:

Dear Enrico  It is quite normal for  the main Contractor to subcontract the MEP works then the MEP subcontractor may subcontract Electrical works who might subcontract It and BMS works. FIDIC does not

2016-05-20 Re measurement/Lumpsum:

Dear Sudatha  17.3 is the SCL that identifies what are the risks associated with the Employer. You need to use this scl when claiming. Ie your case should be identified with such risks.  SCL 19.1 is the

2016-05-18 Re measurement/Lumpsum:

Dear Sudantha  In RE-MEASURABLE CONTRACT you get paid for what you do. So if you install a 150 l heater you get paid for that rate. But if your BOQ has only one rate for a 100 l water heater, then you

2016-05-13 Schedule of payments:

Dear Aziz  FIDI 99 is for re-measured contract. In case you need to have a lump sum contract, you need to delete scl 12.1.  When you do a re-measured contract, the Contract price may be changing every