Construction Law/Expert Profile


Ask A Question

Vineet Shrivastava

Singapore
Available
Expertise

I can answer any question on 1. Project Planning 2. Delay Analysis - Extension of Time 3. Project Management 4. Contract Management 5. Construction Methodology I can't Answer any question 1. Cost related issues

Experience in the area

I have 22 year experience in construction industries at Singapore, India and Australia. I worked as Planning Manager and delay analyst for contractor. I am currently working with claim consultancy as Associate Director.

Organizations

Navigant Consulting APAC Pte Ltd E C Harris Sinagpore Pte Ltd McConnell Dowell SEA Pte Ltd Kajima Oversea Asia Pte Ltd Taisei Corporation

Education/Credentials

B.E (Civil), PGDMA(PM), Graduate Diploma (Const. Management), MSc (Intl. Const. Management),LLM In Construction Law (Arbitration & Adjudication), FSIArb, MCIArb, MIES, MSIB MIIAM, MMIArb

Average Ratings

Recent Reviews from Users

Read More Comments

    K = Knowledgeability    C = Clarity of Response    P = Politeness
UserDateKCPComments
Rakesh03/17/17101010Dear Mr. Vineet, Many many thanks for .....
Rakesh03/16/17101010Dear Mr. Vineet, Many many thanks for .....
Jasna01/04/17101010 
anirudh08/10/16101010Sir, Your insight to my doubt was .....
Aleksandar02/19/16101010 

Recent Answers from Vineet Shrivastava

2017-03-16 How to Carryout time extension analysis:

Dear Rakesh    Thank for your question again.    If the contract states that all 100 km will be given at once, then the contractor is in-principal entitle for extension to time.    Now  the question is

2017-03-16 How to Carryout time extension analysis:

Dear Rakesh    Thank for your question.    You need to evaluate the claim based on contract.    Following conditions need to be satisfy    1. Is a notice of delay was given by the contractor within the

2016-08-10 BOQ:

Dear Anirudh    Even if the item is quantified and ask the Contractor to provide rates for the item, it is not necessary that the item need to be install or construct as the Employer has the right to omit

2016-08-10 BOQ:

Dear Anirudh    Thanks for your question.    URO means - Unit Rate Only  Rate Only means provide the rate of item. The quantity can be measured later.    Generally the Employer ask for the rate of certain

2016-04-27 clarification of condition of contract:

Dear Chandika    Yes Contractor is entitled for revised rate.     BOQ amount = 2,153,500  Actual amount = 10,980,000  %increase in amount = 2,153,500/10,980,000 = 19.6%    Based on this increase in unit

 