Construction Law/Expert Profile

Ask A Question

Vineet Shrivastava


I can answer any question on 1. Project Planning 2. Delay Analysis - Extension of Time 3. Project Management 4. Contract Management 5. Construction Methodology I can't Answer any question 1. Cost related issues

Experience in the area

I have 22 year experience in construction industries at Singapore, India and Australia. I worked as Planning Manager and delay analyst for contractor. I am currently working with claim consultancy as Associate Director.


Navigant Consulting APAC Pte Ltd E C Harris Sinagpore Pte Ltd McConnell Dowell SEA Pte Ltd Kajima Oversea Asia Pte Ltd Taisei Corporation


B.E (Civil), PGDMA(PM), Graduate Diploma (Const. Management), MSc (Intl. Const. Management),LLM In Construction Law (Arbitration & Adjudication), FSIArb, MCIArb, MIES, MSIB MIIAM, MMIArb

Average Ratings

Recent Reviews from Users

Read More Comments

    K = Knowledgeability    C = Clarity of Response    P = Politeness
anirudh08/10/16101010Sir, Your insight to my doubt was .....
Kallol07/07/15Dear Sir, Thanks a lot , Regards - .....
Gadhvi07/02/15101010Well noted, thanks.

Recent Answers from Vineet Shrivastava

2016-08-10 BOQ:

Dear Anirudh    Even if the item is quantified and ask the Contractor to provide rates for the item, it is not necessary that the item need to be install or construct as the Employer has the right to omit

2016-08-10 BOQ:

Dear Anirudh    Thanks for your question.    URO means - Unit Rate Only  Rate Only means provide the rate of item. The quantity can be measured later.    Generally the Employer ask for the rate of certain

2016-04-27 clarification of condition of contract:

Dear Chandika    Yes Contractor is entitled for revised rate.     BOQ amount = 2,153,500  Actual amount = 10,980,000  %increase in amount = 2,153,500/10,980,000 = 19.6%    Based on this increase in unit

2016-04-25 Why Performance Guarantee & Liquidated Damages Are Not Applicable in Consultancy Services Contracts:

Dear Mr. Adil    The question is how will you measure performance of consulting company. In case of construction contract, you measure the performance of contract by the works done by the Contractor against

2016-03-11 Claims.:

Dear Mr. Natarajan    Thanks for your question and sorry for late reply.    I hope you know what is prolongation cost. It is the actual time related cost (Cost of Equipment, Staff and labor etc.) incurred


Ask A Question

Construction Law

All Answers

Answers by Expert:

Ask Experts


©2016 All rights reserved.