Construction Law/Expert Profile


Ask A Question

Expertise

I may answer to the questions relating to FIDIC 4th as well as FIDIC 2010 MDB Harmonized version,price adjustment ,Variations,Eot and Cost claims,EPC Contract,Bidding Document,consultancy Contracts,certification,Standard Forms, Dispute resolution; and others pertaining to Contract implementation.

Experience in the area

Contract management and Contract Administration, using FIDIC Conditions of 4th Addition as well as Fidic 1999 Red, Yellow and Silver Books including MDB Harmonized Edition 2010. Particularly in the area of Procurement of Contracts, Certification,Price Adjustment, variations,disputes management, EoT and Cost Claims; and other contractual issues arises from time to time during currecy of the Contracts.

Organizations

Member -Pakistan Engineering Council Member -Pakistan Engineering Congress Member -FIDIC Organisation

Publications

Joint Venture and Consortium Agreements for Pakistan Engineering Council,Pakistan

Education/Credentials

BSc Civil Engineering; Basic Management course; Hydro power Projects; and various other on Job Trainings

Awards and Honors

Commendation Certificate for the excellent management qualities and dedication at Ghazi Barotha Hydropower Project; and Certificate of Excellent work performed during Survey Camp.

Past/Present Clients

Water and Power Development Authority (WAPDA),Associate Consulting Engineer(ACE) and National Engineering services Pakistan(Pvt.) Limited (NESPAK)

Average Ratings

Recent Reviews from Users

Read More Comments

    K = Knowledgeability    C = Clarity of Response    P = Politeness
UserDateKCPComments
Tapas Chattopadhyay02/19/17101010Thank you :)
dhafir02/06/17 
shoaib12/22/1610GOOD
Prem10/27/16101010Mr Arshad's answers are full of clarity .....
Shantha09/06/16101010Thank you very much sir, for the .....

Recent Answers from Arshad Mahmood

2017-02-17 Applicability of GC Sub-clause 12.3.4 for new rate of BOQ Item in FIDIC Bank Harmonised edition:

Dear Tapas,  Straight forward, I would say ,It will apply to the balance quantities.The logic behind that,the Contractor has offered his rate for the BOQ quantities which are estimated one.However, the

2017-02-03 variation claim for lump sum item (de-watering):

Dear dhafir,     If the delay is totally attributable to the Employer and the Contractor is not involved in the this delay.Then, the Contractor is entitled @ the given rate ,provided he has timely notified

2017-01-22 Price Adjustment:

Dear Muhammad  Would you please tell the  time duration and nature of Work of your project besides the applicable  conditions of Contract;without which it is not possible to give detailed  specific answer

2016-10-23 Billing:

In the presence of the provision  specified in your follow-up question,the Client may deduct and try to deduct the rental value. But truly speaking it would not be fair to deduct the rental value because

2016-10-21 Billing:

Dear Prem,     Generally,in Lumpsum Contract,there is no change in  contract cost and the Employer cannot reduce the scope of work.However, if there is some provision exists in the Contract,the Employer

 