Construction Law/Expert Profile


Ask A Question

Expertise

I can answer to claims assesments under FIDIC 4 and under FIDIC red book; I can answer to procedural issues under FIDIC rules; DAB implementation DAB procedures, etc

Experience in the area

8 years in consulting companies, road contracts (rehabilitation and new) more than 250 Milion Euro supervision Contracts

What do you like about this subject?

It is always a challenge in finding a balance between what you expect and what you achieve. Between two bad things you have to find the best solution.

What do you still hope to achieve/learn in this field?

A good solution it is a solution for progress.The life and experience and an open mind taught peoples to progress. Balance between solutions and opportunities are a way of progress.

Something interesting about this subject that others may not know:

Contractor - Employer linked by a Contract. The issues on both sides have to be measured with the same device.

Something controversial or provocative about this subject

Sometimes the judges forgive the hawks and penalize the small birds.

Average Ratings

Recent Reviews from Users

Read More Comments

    K = Knowledgeability    C = Clarity of Response    P = Politeness
UserDateKCPComments
mututantree05/17/12101010Thanks for the prompt reply. It is .....
Mututantree03/09/12101010 
Mututantree03/05/12101010 
Mututantree01/25/12101010 
Mututantree01/22/12101010 

Recent Answers from Bogdan Oprea

2012-05-15 construction law:

Dear Sir,  We hat to remind that FIDIC pink book is a re-measurement Contract and the Bill of Quantities are only estimates of the works to be executed (see sub-clause 14.1)  For the evaluation of new

2012-04-20 FIDIC - ELECTRICAL AND MECHANICAL WORKS 1987- RELEASE OF RETENTION:

Dear Sir,  The performance guarantee has been claimed correctly since the Contractor could not extend it.  Probably this contract will be terminated and if it will be due to the Contractor’s fault the

2012-03-05 Construction law:

The Employer in the BOQ put the quantities and the Contractor put his rates, therefore it is his risk.   In this type of contract the Contractor is obliged to do the works in accordance with the BOQ rates

2012-02-28 Construction Law:

There are 2 issues:  1. If the Contractor put the low rates than he is responsible and he will have to do the work accordingly because he is responsible for the calculation of the Accepted Contract Amount

2012-02-23 Construction Law:

Dear Sir,  Pending on what is mentioned in the Contract between the main Contractor and the nominated Sub-conatractor.  If something like the following is mentioned:  (a) the subcontract does not specify

 

Ask A Question

Construction Law

All Answers


Answers by Expert:


Ask Experts

Volunteer


©2012 About.com, a part of The New York Times Company. All rights reserved.