2008-09-14 Claim for Extension of Time - Unremoved Services: The first thing to be done is to collect all this evidences and make a proper file. Including all corresponds and any other document that may support your EOT. Then first you shall send a simple letter...
|
2008-09-14 Inspection under FIDIC 4: If there is not any special clause in your contract, 28 days is the time for the Engineer to reply. But please check your special conditions if any other time frame is specified or not. Contractor can...
|
2008-09-07 Remedy: It is important that, whose responsibility was the design of structure. If it is a design and built contract and it is contractor scope of work to design the structure, yes Employer can claim. So it...
|
2008-08-29 Scope of work under FIDIC Contract for Plant and Design-Build Project: The scope of work is described in the General Specification. If there is any change from the General Spec. that is described in the Particular Spec. You shall check first the Particular spec. to find out...
|
2008-08-24 construction programme: You shall call it Revised program and submit with submittal form for the approval of consultant. Just after you receive their approval or 28 days later of your submittal if consultant does not reply you...
|